There will be outages in the winter of 2024-25 and spring of 2025. We recommend that researchers consider the possibility of such outages when planning research programs, graduate examinations, etc., for next winter and spring.
There will be outages in the winter of 2024-25 and spring of 2025. We recommend that researchers consider the possibility of such outages when planning research programs, graduate examinations, etc., for next winter and spring.
}}
}}
= Status =
For current outages please see the status pages.
{| class="wikitable"
|-
| Sep 13, 2024 || All sites except McGill have completed their RFP processes and have sent Purchase Orders to vendors. The McGill (Rorqual) storage RFP is still open and is scheduled to complete on Sep 18.
* All sites are working on infrastructure (power and cooling) design and implementation. We are expecting some outages over the autumn for cabling and plumbing upgrades, and will update this page when we know more. 
|-
| Sep 3, 2024 || Currently all sites have completed Requests for Proposals, and are working with the vendors on deliverables and purchase orders. 
|}